Springwood Station

Location:

Springwood, Blue Mountains
Client:
Shreeji Consultant / Sydney Trains
Duration:
1 possession weekend

While small, this project was significant in terms of the short delivery window available to us – a single possession weekend – and the Heritage aspects of the station requiring protection. The work involved saw-cutting of the platform surface to expose the footings around the columns supporting the station building roof, as some showed evidence of sinking. The project is testament to Rapid’s ability to respond quickly and deploy a team during weekend possession to investigate issues, as well as our willingness to take on smaller and technically more challenging tasks. Small portable conveyors were deployed across the tracks to permit fast and clean removal of excavated spoil and delivery of stabilising base material into the excavations.