Clyde Signal Box – Hazardous Materials Removal

Location:

Clyde Signal Box - Rail Corridor Main Western Line
VALUE:
$150k
Client:
Sydney Trains
Duration:
Single possession weekend in 2011

Removal and disposal of all internal asbestos linings and complete relining and electrical re-wiring of the interior of the building, as well as new kitchen and amenities. The work was fully completed within one possession weekend utilising multiple back-to-back shifts in order not to interfere with the normal operation of the Signal Box, which is normally operational 24/7. The kitchen was also replaced and the building fully repainted inside and out – these works were completed during normal hours as they did not affect normal signal box operations. The building is wholly within the rail corridor and existed at the time within the site boundary of another builder’s site – Rapid’s team was inducted by this company and our safety and environmental documentation and methodologies reviewed and approved by them.